The Reconstruction of The Karantina Hospital

The Project consists of the complete demolition of the existing old hospital Building (Building A) and the reconstruction of a new hospital building. The total number of in-patient beds is around 70 (including 6 ICUs and 3 CCUs). All patient rooms are 2 bedded rooms, except the isolation negative pressure rooms

The Project consists of the complete demolition of the existing old hospital Building (Building A) and the reconstruction of a new hospital building. The total number of in-patient beds is around 70 (including 6 ICUs and 3 CCUs). All patient rooms are 2 bedded rooms, except the isolation negative pressure rooms

Location

Beirut, Lebanon

Client

Qatar Fund for Development

Engineer

Dar Al Handasah

Built Up Area

11,984 sqm

Project Duration

24 months