MV6 Data Center

The MV6 Data Centre project for Meeza is a 16-month development on a greenfield site of approximately 45,000 m², located adjacent to Meeza’s existing MV2 Data Centre at Umm Garn.

The project is scheduled to complete on 14th April 2028, with a total value of QAR 130,000,000. The facility is planned to have an initial IT capacity of 6 MW on day one, with provisions for future expansion in two additional phases—Phase Two adding 14 MW and Phase Three adding 4 MW, bringing the total IT load to 24 MW.

MAN’s scope of work covers the civil, structural, architectural, and finishing works for the entire project.

Location

Doha, Qatar

Client

Meeza

Consultant

DSG

Start Date

December 2026

Project Duration

16 months