Gewan Island Car Park

The Gewan Island Carpark project for the United Development Company is a design-and-build assignment with a duration of 12 months, starting on 1st March 2026 and scheduled for completion on 28th February 2027, with a total project value of QAR 30,000,000.

The project is located near the Gewan Mosque and the existing Gewan Clubhouse, along Al Masjid Street. It consists of a four-story reinforced concrete structure (G+4) with rooftop shaded parking, designed to accommodate approximately 390 vehicles. The facility includes two passenger lifts, one service lift, and a ticketless ANPR-based parking system.

Location

Doha, Qatar

Client

United Development Company

Project Duration

12 months