The Dora Viaduct Project consists of the construction of two parallel bridges of 500m length each, in addition to the rehabilitation of all the infrastructure under the bridge.
The Dora Viaduct Project consists of the construction of two parallel bridges of 500m length each, in addition to the rehabilitation of all the infrastructure under the bridge.
Location
Dora, Lebanon
Client
Council of Development & Reconstruction (CDR)
Consultant
Dar El Handassah (Nazih Taleb)
Built Up Area
4,500 m²
Start Date
March 2006
Project Duration
33 months